Granted

Avenue de l'Héliport 9

Bruxelles · 04/IPEPLP/1869675 · Prolongation de PE

Avenue de l'Héliport 9, Bruxelles: operation of installations. Case octroyé, lodged on 20 January 2023. The decision was notified on 8 January 2024, 353 days after lodging.

Exploitation d'un poste haute tension
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on20 January 2023date the file was received
Decision notified8 January 2024353 days
Works started21 January 2024
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
18 mTree fellingAbattre trois arbres à haute tige (Fraxinus pennsylvanica Marshall) situé sur le terrain jouxtant le poste électrique ha2025
52 mExtension or raisingfermer une terrasse2023
60 mFaçade and windowsd'une part, changer les châssis(mise en conformité) ; d'autre part, peindre la façade et remplacer la corniche2022
100 mChange of useconstruire une extension arrière, transformer une maison unifamiliale avec magasin au rez-de-chaussée en 3 logements (2 2026
113 mExtension or raisingconstruire une annexe en toiture (mise en conformité)2024

Other nearby cases : 04/PU/2025440, 04/SFD/1870584, 04/PFD/1858554, 04/PU/1931137, 04/GOU_PU/1948754, 04/PFD/1922757, 04/PU/1910301, 04/PFD/1934364, 04/PU/1929336, 04/PU/2043512, 04/PU/1946219, 04/PU/1957416, 04/PU/1856889, 04/SFD/1827127, 04/PU/2021888, 04/PU/1950211, 04/PU/1916434, 04/PFD/1832470, 04/PFD/1925816, 04/PFU/1910815, 04/PU/1938480, 04/SFD/1971702, 04/PU/1867723, 04/PU/1829036, 04/PU/1896528

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)