Rue de Heembeek 241–247
Bruxelles · 04/IPEPLP/1967006 · Prolongation de PE
Rue de Heembeek 241–247, Bruxelles: operation of installations. Case octroyé, lodged on 11 December 2024. The decision was notified on 21 November 2025, 345 days after lodging.
Exploitation d'un immeuble de logements
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 December 2024 | date the file was received |
| Decision notified | 21 November 2025 | 345 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Public space | Créer une ligne de tramway (T10) et aménager l'espace public entre l'avenue des Croix de Feu et la rue Bruyn ; réaménage | 2022 |
| 42 m | Extension or raising | rehausser le niveau de toiture | 2025 |
| 49 m | Retail or horeca fit-out | placer des paravents fixes attenants à une terrasse d’un commerce avec possibilité de consommer sur place | 2025 |
| 61 m | Façade and windows | remplacer l'ensemble des châssis et la porte d'entrée en façade avant | 2022 |
| 61 m | Façade and windows | remplacer l'ensemble des châssis et la porte d'entrée en façade avant | 2023 |
Other nearby cases : 04/PU/1929834, 04/PU/1896716, 04/PU/1953336, 04/PU/1930275, 04/PU/1892467, 04/PU/1947450, 04/PU/1947447, 04/PU/1968327, 04/PU/1864372, 04/PU/1989572, 04/PU/1961627, 04/PU/1990061, 04/PU/1943697, 04/PU/1853298, 04/PU/2017402, 04/PU/2029750, 04/PU/1921758, 04/PU/1998128, 04/SFD/1866121, 04/PU/1924747, 04/PU/1895480, 04/PU/1897282, 04/PU/2041110, 04/PU/1961080, 04/PU/2042120
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)