Skip to content
AltUrb
Granted

Square de la Cité Modèle 1

Bruxelles · 04/IPEPLP/1984357 · Prolongation de PE

Square de la Cité Modèle 1, Bruxelles: operation of installations. Case octroyé, lodged on 10 April 2025. The decision was notified on 9 April 2026, 364 days after lodging.

Prolongation du permis d'environnement 653.722
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on10 April 2025date the file was received
Decision notified9 April 2026364 days
Works started11 April 2026
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
81 mPublic spaceRéaliser des travaux de GIEP (Gestion intégrée des eaux pluviales et végétalisation) sur la cité Modèle à 1020 Laeken.2025
101 mOtherenlever et placer un mat pour antennes d'une hauteur de 16 m sur le toit d'un immeuble2024
101 mOtherenlever et placer un mat pour antennes d'une hauteur de 16 m sur le toit d'un immeuble2024
104 mExtension or raisingÉtendre et aménager l'espace culturel Braem et créer une rampe de livraison2026
185 mTree fellingabattre 2 arbres2025

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)