Withdrawn
Chaussée de Vilvorde 300
Bruxelles · 04/IPEPLP/446153 · Prolongation de PE
Chaussée de Vilvorde 300, Bruxelles: operation of installations. Case annulé, lodged on 11 May 2005. The decision was notified on 6 September 2005, 118 days after lodging.
exploitation d'un site d'exercices d'incendie| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 11 May 2005 | date the file was received |
| Decision notified | 6 September 2005 | 118 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 129 m | New construction | construire une cabine électrique de 8.95 m² | 2025 |
| 129 m | New construction | construire une cabine électrique de 9.13 m² (mise en conformité) | 2026 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)