Skip to content
Altaica Urban
Withdrawn

Rond-Point Robert Schuman 6

Bruxelles · 04/IPEPLP/448133 · Prolongation de PE

Rond-Point Robert Schuman 6, Bruxelles: —. Case annulé, lodged on 23 June 2006. The decision was notified on 22 December 2006, 182 days after lodging.

Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on23 June 2006date the file was received
Decision notified22 December 2006182 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
36 mTree fellingabattre un arbre à haute tige2026
70 mSigns and advertisingplacer 5 enseignes2022
70 mRetail or horeca fit-outTransformer un rez-de-chaussée commercial en Shell-café avec 2 espaces de réunion ; remplacer les châssis ; fermer une o2023
70 mChange of usetransformer une station-service en station de charge pour véhicules électriques2022
70 mSigns and advertisingPlacer une enseigne parallèle "Shel Café" supplémentaire à la façade en recul côté avenue d'Auderghem2023

Other nearby cases : 04/SFD/1864499, 04/PU/1845610, 04/PFD/1856721, 04/PU/1831218, 04/PU/1953768, 04/PU/1938157, 04/PU/1931492, 04/PU/1924331, 04/GOU_PU/2011596, 04/PU/1844358, 04/SFD/1898359, 04/PU/1966034, 04/PU/1957326, 04/PU/1978304, 04/PU/2008787, 04/PFD/2024927, 04/PFD/1966933, 04/PU/1965751, 04/PFD/1964137, 04/PFD/2040376, 04/PU/1958870, 04/PFD/1850103, 04/GOU_PU/1987348, 04/PU/1944259, 04/PU/1980862

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)