Skip to content
Altaica Urban
Granted

Boulevard Emile Jacqmain 53

Bruxelles · 04/IPEPLP/489939 · Prolongation de PE

Boulevard Emile Jacqmain 53, Bruxelles: —. Case octroyé, lodged on 15 July 2013. The decision was notified on 11 December 2014, 514 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on15 July 2013date the file was received
Decision notified11 December 2014514 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingdémolir et étendre l’étage technique (8ème étage) afin de placer deux nouvelles pompes à chaleur2023
0 mHeavy renovationapporter des transformations structurelles intérieures : supprimer une colonne et placer deux poutres2023
33 mPublic spaceAdapter un terminus provisoire du B88 – Implantation d’une sanisette mixte – Changement du revêtement pierres naturelles2023
35 mRetail or horeca fit-outtransformer un rez-de-chaussée commercial en un snack, changer la devanture commerciale et démonter une partie de la mez2022
49 mExtension or raisingaménager un logement sous combles dans un immeuble de rapport avec modification de volume (création de 2 lucarnes en faç2022

Other nearby cases : 04/PU/1861646, 04/PU/1935470, 04/PFU/1986956, 04/PFU/1860435, 04/PU/1958918, 04/PFD/1975364, 04/PU/2019848, 04/PU/1967950, 04/PU/1821556, 04/PFU/1936399, 04/PU/1937870, 04/PFU/1937918, 04/PU/1938070, 04/PU/2037564, 04/PU/2034232, 04/PFU/1988631, 04/PFD/1852767, 04/PU/1853282, 04/PU/1906806, 04/PU/1927340, 04/PU/1801558, 04/PU/2033566, 04/PU/1824432, 04/PU/1822681, 04/PU/1849880

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)