Boulevard Bischoffsheim 29–33

Bruxelles · 04/IPEPLP/495559 · Prolongation de PE

Boulevard Bischoffsheim 29–33, Bruxelles: —. Case octroyé, lodged on 17 December 2013. The decision was notified on 18 November 2015, 701 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on17 December 2013date the file was received
Decision notified18 November 2015701 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
21 mSigns and advertisingplacer une publicité sur une bâche de chantier2023
50 mExtension or raisingd'une part, aménager 4 unités de logement et modifier la façade à rue en plaçant de nouveaux châssis et un nouvel enduit2025
90 mTree fellingabattre un arbre (Tilleul)2026
103 mTree fellingabattre un arbre (Tilleul)2025
106 mSigns and advertisingPlacer une plaque en cuivre en façade pour indiquer la présence de la Région Auvergne-Rhône-Alpes dans l'immeuble.2024

Other nearby cases : 04/PU/2024126, 04/PU/1988625, 04/PU/1980355, 04/PFD/1869209, 04/PFU/1975858, 04/PFU/1918933, 04/PU/1914689, 04/PFU/1973256, 14/PU/1959103, 04/PFD/2027039, 04/PU/1855730, 04/PU/1993134, 04/PU/1895287, 14/PU/1844189, 04/PU/1849661, 04/GOU_PU/1914079, 04/SFD/1909579, 04/PFD/1859333, 04/PFD/2040741, 14/PFD/1970278, 14/PU/1891809, 14/PFD/1902535, 14/PU/1965079, 14/SFD/1994331, 14/PU/1978410