Granted

Rue Joseph Stevens 7

Bruxelles · 04/IPEPLP/561668 · Prolongation de PE

Rue Joseph Stevens 7, Bruxelles: —. Case octroyé, lodged on 2 April 2015. The decision was notified on 25 April 2016, 389 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on2 April 2015date the file was received
Decision notified25 April 2016389 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
36 mPublic spaceplacer 1 mobilier urbain d’information avec support de publicité (BXL0468)2021
54 mHeavy renovationTransformer le Musée Juif de Belgique.2022
56 mNew constructiond'une part installer une grille coulissante (mise en conformité); d'autre part construire une cabine à haute tension et 2022
59 mMerger of dwellingsmodifier le permis J389/2020 délivré le 10/06/2021, réunir les deux logements du 6ème étage en un seul logement de 3 cha2022
59 mSigns and advertisingplacer une publicité sur bâche de chantier2021

Other nearby cases : 04/SFD/1845913, 04/PU/1900536, 04/PU/1831790, 04/PU/1833880, 04/PU/1924080, 04/PU/1828723, 04/PU/2039568, 04/PU/1801273, 04/PFD/1868941, 04/PU/1981878, 04/PU/1944208, 04/PU/1999650, 04/PU/2020293, 04/PFU/2006374, 04/PFU/1962465, 04/GOU_PU/2001452, 04/PFU/1899366, 04/PU/2034685, 04/PU/1896951, 04/PFU/1956724, 04/PFU/2004627, 04/PU/2004660, 04/SFD/1977664, 04/PU/1956888, 04/PU/1826705

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)