Granted
Rue du Dobbelenberg 20
Bruxelles · 04/IPEPLP/578169 · Prolongation de PE
Rue du Dobbelenberg 20, Bruxelles: operation of installations. Case octroyé, lodged on 20 August 2015. The decision was notified on 19 July 2016, 334 days after lodging.
Vernieuwing van vergunning voor een fabrikant van eretekens, medailles, munten en penningen| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 August 2015 | date the file was received |
| Decision notified | 19 July 2016 | 334 days |
| Works started | 28 August 2016 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Heavy renovation | créer des bureaux et des sanitaires pour l'entrepôt dans le bâtiment existant, rénover la façade, démolir un auvent et r | 2022 |
| 86 m | Tree felling | Heraanleg terrein en bouw keermuren (zie verklarende nota) | 2024 |
| 86 m | Tree felling | Réaménager le terrain et construire des murs de soutènement (mise en conformité partielle). | 2025 |
| 164 m | Change of use | aménager un logement complémentaire et accessoire (74m²) au troisième étage d'un immeuble industriel destiné à un entrep | 2025 |
| 209 m | Public space | Voor het project Border Buda, een samenwerking tussen Brussel, Machelen en Vilvoorde, werd een kunstwerk geplaatst op he | 2024 |
Other nearby cases : 04/PFD/1955650
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)