Granted

Rue Claessens 57–59

Bruxelles · 04/IPEPLP/598396 · Prolongation de PE

Rue Claessens 57–59, Bruxelles: operation of installations. Case octroyé, lodged on 13 April 2016. The decision was notified on 13 April 2017, 365 days after lodging.

Exploitation d'un établissement scolaire avec développement photographique
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on13 April 2016date the file was received
Decision notified13 April 2017365 days
Works started16 April 2017
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
54 mPublic spacemaintenir un mobilier urbain d’information avec support de publicité (BXL0469)2024
72 mFaçade and windowsmodifier les châssis et la couleur de la façade avant;2021
85 mSigns and advertisingplacer 1 mobilier urbain d'information avec support de publicité (BXL0469)2022
85 mSplit into dwellingsdiviser une maison unifamiliale en 3 logements (2 duplex 3 chambres et 1 studio), changer la destination d’un ancien ent2025
111 mExtension or raisingd’une part, construire une annexe au rez-de-chaussée, rehausser le mur mitoyen droit et remplacer les châssis en façade 2026

Other nearby cases : 04/PU/1843411, 04/PU/1868842, 04/PU/2013995, 04/PU/1831726, 09/PFU/1893192, 04/PU/1939180, 04/PFD/1972375, 04/PU/1972885, 04/PFD/2005933, 04/PU/1946598, 04/SFD/1855226, 04/PU/1840597, 04/PU/1831763, 04/PU/1831724, 04/PU/1957427, 04/PU/1907559, 04/PU/1922433, 04/PU/1904147