Font Saint Landry 3

Bruxelles · 04/IPEPLP/598463 · Prolongation de PE

Font Saint Landry 3, Bruxelles: operation of installations. Case octroyé, lodged on 18 April 2016. The decision was notified on 19 July 2017, 457 days after lodging.

exploitatie van een industrieelgebouw met bijhorend parkeerterrein
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on18 April 2016date the file was received
Decision notified19 July 2017457 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
144 mDemolition and reconstructionDémolir et reconstruire un hangar, un bureau et un parking semi-enterré2024
199 mOtherinstaller une clôture métallique ajourée autour du site Novo Nordisk Production Belgium2026
200 mNew constructionconstruire un Cuve Aérienne de Saumure (mise en conformité)2023
200 mOtherplacer 4 conteneurs dont 2 frigorifiques avec 1 sas logistique, et 2 zones de stockage, et modifier le relief de 60 cm (2025
202 mExtension or raisingEtendre des infrastructures existantes permettant la création d'une unité moderne et autonome de lignes de remplissage. 2026

Other nearby cases : 04/PU/1995444