Granted

Avenue de Vilvorde 126

Bruxelles · 04/IPEPLP/631600 · Prolongation de PE

Avenue de Vilvorde 126, Bruxelles: operation of installations. Case octroyé, lodged on 10 March 2017. The decision was notified on 9 March 2018, 364 days after lodging.

Demande de prolongation pour l’exploitation d’une unité du réseau de transport de haute tension, d’un bâtiment technico-administratif et d’un parc à câbles.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on10 March 2017date the file was received
Decision notified9 March 2018364 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mHeavy renovationrenoveren van de wachtloge op de site van Elia2022
74 mNew constructionPlacer de nouveaux containers de bureaux en remplacement de containers temporaires sur le site d'Electrabel.2023
90 mSigns and advertisingplacer deux dispositifs publicitaires sur pieds, de 20m² chacun non-éclairé (mettre en conformité)2026
115 mDemolition and reconstructiondémolir et reconstruire un container servant de bureau2023
115 mDemolition and reconstructiondémolir et reconstruire un container servant de bureau2023

Other nearby cases : 04/PFD/1972777, 04/PFU/1860340, 04/PFD/1942111, 04/PU/1865361, 04/SFD/1913148, 04/PFD/1996155