Granted
Rue de la Fusée 50
Bruxelles · 04/IPEPLP/631659 · Prolongation de PE
Rue de la Fusée 50, Bruxelles: —. Case octroyé, lodged on 16 March 2017. The decision was notified on 26 February 2018, 347 days after lodging.
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 March 2017 | date the file was received |
| Decision notified | 26 February 2018 | 347 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 110 m | Signs and advertising | placer deux enseignes parallèles lumineuses en lettres boîtiers sur deux façades du bâtiment existant (portant l'inscrip | 2026 |
| 110 m | New construction | implanter une cabine de tête haute tension | 2025 |
| 120 m | Extension or raising | Installer deux bornes de recharges pour véhicules électriques et construire 4 places de stationnement spécifiques. Inst | 2022 |
| 120 m | Other | = complément du dossier F3038/2022 | 2023 |
| 120 m | Energy works | placer 1 station de charge pour voitures électrique pour 2 emplacements de parking sur le parking existant | 2022 |
Other nearby cases : 04/PU/1923116, 04/PU/1857175, 04/PU/1926812, 04/PU/2031863, 04/PFD/1823459, 04/PFD/1991831
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)