Skip to content
Altaica Urban
Granted

Rue de la Fusée 98

Bruxelles · 04/IPEPLP/700390 · Prolongation de PE

Rue de la Fusée 98, Bruxelles: —. Case octroyé, lodged on 27 September 2018. The decision was notified on 27 October 2019, 395 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on27 September 2018date the file was received
Decision notified27 October 2019395 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of useRéaffecter l'entrée principale et une partie du 1er étage du bloc A, d'activité productive de biens matériels (data cent2022
67 mNew constructionagrandir la structure existante de l'entreprise avec une nouvelle aile industrielle, construire un nouveau bâtiment avec2023
92 mNew constructionEtendre des bâtiments et ajouter un nouveau bâtiment2023
92 mNew constructionagrandir la structure existante de l'entreprise avec une nouvelle aile industrielle (519m²), construire un nouveau bâtim2023
206 mPublic spaceCréer une zone de remisage tram nocturne par la sécurisation du terminus existant « Eurocontrol » 2024