Withdrawn
Quai des Armateurs
Bruxelles · 04/IPETMP/1843607 · Permis d'environnement temporaire
Quai des Armateurs, Bruxelles: operation of installations. Case annulé, lodged on 25 May 2022. The decision was notified on 22 June 2022, 28 days after lodging.
exploitation d'un dépôt de boues| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 25 May 2022 | date the file was received |
| Decision notified | 22 June 2022 | 28 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | New construction | Construire une tour sportive comprenant une cafétaria publique au RDC, une salle d'escalade, une salle de gym et une sal | 2024 |
| 62 m | Signs and advertising | maintenir un mobilier urbain d’information avec support de publicité (BXL0474) | 2024 |
| 77 m | New construction | Réhabiliter et étendre sur deux niveaux une crèche communale néerlandophone, construire 11 logements et réaliser un jard | 2025 |
| 88 m | Change of use | changer la destination du 1er étage d’un atelier lié au commerce de détail du rez-de-chaussée en un logement 2 chambres | 2025 |
| 93 m | Signs and advertising | placer 2 dispositifs publicitaires de 17 m² | 2023 |
Other nearby cases : 04/GOU_PU/1910018, 04/PU/1866583, 04/PFD/1828253, 04/PFD/1984816, 04/PFD/2038859, 04/PFD/1948499, 04/PU/1801293, 04/PU/1907838, 04/PFD/1947976, 04/PU/1845990, 04/SFD/1896893, 04/GOU_PU/1907689, 04/PU/1936350, 04/PU/1827897, 04/SFD/1825000, 04/PU/1895758, 04/PU/1838593, 04/PFD/2033397