Rue du Boulet 29
Bruxelles · 04/IPETMP/458634 · Permis d'environnement temporaire
Rue du Boulet 29, Bruxelles: —. Case annulé, lodged on 25 May 2011. The decision was notified on 29 June 2011, 35 days after lodging.
| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 25 May 2011 | date the file was received |
| Decision notified | 29 June 2011 | 35 days |
| Works started | 5 September 2011 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 40 m | Change of use | changer la destination du bâtiment en intérieur d’îlot d’activités industrielles en équipement (centre culturel Globe Ar | 2025 |
| 55 m | Heavy renovation | Rénover et ouvrir au quartier le gymnase et la salle des fêtes de l'école. | 2024 |
| 60 m | Change of use | Régularisation de l'affectation d'un immeble à rez-de-chaussée commercial et deux niveaux de logement | 2024 |
| 60 m | Change of use | changer l'utilisation du rez-de-chaussée de commerce de détail en commerce de service (pressing), diminuer le gabarit d' | 2024 |
| 69 m | Change of use | modifier la destination et la répartition des espaces de commerce situés au rez-de-chaussée et au sous-sol en bureau, ét | 2026 |
Other nearby cases : 04/PU/1845629, 04/PU/1825425, 04/PU/1912743, 04/PU/2010206, 04/PU/1966550, 04/SFD/1840955, 04/PU/1827129, 04/PU/1834590, 04/PFD/1962150, 04/PU/1845784, 04/PU/1865797, 04/PFD/1927157, 04/PFD/2036161, 04/PFD/2042402, 04/PU/1862223, 04/PU/1897845, 04/PU/1995411, 04/PU/1830652, 04/PU/1830647, 04/PU/1856985, 04/PU/1919048, 04/PU/1901330, 04/PU/1850540, 04/PFU/1913023, 04/PFU/2037151
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)