Carrefour de l'Europe 2, Bruxelles: demolition. Case annulé, lodged on 18 November 2013. The decision was notified on 5 February 2014, 79 days after lodging.

werf voor asbestverwijdering
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on18 November 2013date the file was received
Decision notified5 February 201479 days
Works started25 February 2014
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Decision notified · Withdrawn
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.