Withdrawn
Boulevard Adolphe Max 118
Bruxelles · 04/IPETMP/542897 · Permis d'environnement temporaire
Boulevard Adolphe Max 118, Bruxelles: operation of installations. Case annulé, lodged on 1 July 2014. The decision was notified on 5 August 2014, 35 days after lodging.
Chantier Amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 1 July 2014 | date the file was received |
| Decision notified | 5 August 2014 | 35 days |
| Works started | 27 July 2015 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.