Withdrawn
Passage Saint-Honoré
Bruxelles · 04/IPETMP/572492 · Permis d'environnement temporaire
Passage Saint-Honoré, Bruxelles: operation of installations. Case annulé, lodged on 20 July 2015. The decision was notified on 24 August 2015, 35 days after lodging.
Chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 20 July 2015 | date the file was received |
| Decision notified | 24 August 2015 | 35 days |
| Works started | 14 August 2015 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Works started
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.