Granted
Avenue de Madrid 100
Bruxelles · 04/PFD/122630-01 · Permis d'urbanisme délivré par le FD
Avenue de Madrid 100, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 8 April 1999. The decision was notified on 17 November 2000, 589 days after lodging.
démolir un pavillon côté av. de l'Atomium + installer 3 nouveaux pavillons préfabriqués côté av. de l'Atomium
à usage d'école (1,885m2),| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 April 1999 | date the file was received |
| Consultation committee | 21 March 2000 | |
| Decision notified | 17 November 2000 | 589 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 121 m | Signs and advertising | remplacer 1 mobilier urbain d’information avec support de publicité (BXL0463) (mise en conformité) | 2021 |
| 161 m | Public space | Installer l'œuvre d'art "Onument" au Parc d'Osseghem | 2022 |
| 161 m | Public space | Installer l'œuvre d'art "Onument" au Parc d'Osseghem | 2023 |
| 238 m | Other | Organiser un événement de deux jours avec quatre scènes au Parc d'Osseghem | 2022 |
| 240 m | Change of use | modifier la destination de commerce en équipement (fietspolitie) | 2024 |
Other nearby cases : 04/PFD/1966926, 04/PFU/1869737, 04/PFU/1870737
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)