Granted
Quai des Usines 16
Bruxelles · 04/PFD/127199 · Permis d'urbanisme délivré par le FD
Quai des Usines 16, Bruxelles: new construction. Case octroyé, lodged on 23 December 1999. The decision was notified on 28 February 2001, 433 days after lodging.
construire une station de détente gaz naturel avec récupération électrique| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 December 1999 | date the file was received |
| Consultation committee | 21 March 2000 | |
| Decision notified | 28 February 2001 | 433 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Signs and advertising | placer un dispositif de publicité | 2023 |
| 0 m | Signs and advertising | Placer un cadre pour annonce d'embauche sur le pignon du bâtiment A. | 2023 |
| 109 m | Signs and advertising | maintenir 1 mobilier urbain d’information avec support de publicité (BXL 0593) | 2024 |
| 147 m | Office conversion | Transformer et réaffecter un bâtiment de bureaux existant (commissariat) en un immeuble de 60 logements avec extension l | 2024 |
| 162 m | Signs and advertising | Maintenir 2 panneaux publicitaires éclairés d'une superficie de 16 m² et 36 m², situés sur le Quai des Usines à l’arrêt | 2025 |
Other nearby cases : 04/GOU_PU/1907814, 04/PU/1956696, 04/PFD/1868120, 04/PU/1862688, 04/PU/1916463, 04/PFD/1825881
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)