Granted
Place Arthur Van Gehuchten 4
Bruxelles · 04/PFD/136888 · Permis d'urbanisme délivré par le FD
Place Arthur Van Gehuchten 4, Bruxelles: new construction. Case octroyé, lodged on 11 May 2001. The decision was notified on 23 January 2002, 257 days after lodging.
Construire une installation de cogénération sur le site du CHU Brugmann| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 May 2001 | date the file was received |
| Decision notified | 23 January 2002 | 257 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)