Place Arthur Van Gehuchten 4

Bruxelles · 04/PFD/138145 · Permis d'urbanisme délivré par le FD

Place Arthur Van Gehuchten 4, Bruxelles: new construction. Case octroyé, lodged on 7 August 2001. The decision was notified on 8 August 2002, 366 days after lodging.

installation d'une unité provisoire de bureaux modules préfabriqués pour une durée de 36 mois bâtiment U
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on7 August 2001date the file was received
Decision notified8 August 2002366 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.