Skip to content
Altaica Urban
Granted

Quai des Usines

Bruxelles · 04/PFD/155969 · Permis d'urbanisme délivré par le FD

Quai des Usines, Bruxelles: new construction. Case octroyé, lodged on 30 April 2004. The decision was notified on 29 November 2004, 213 days after lodging.

Construire un bâtiment industriel
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on30 April 2004date the file was received
Decision notified29 November 2004213 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)