Granted
Esplanade
Bruxelles · 04/PFD/161795 · Permis d'urbanisme délivré par le FD
Esplanade, Bruxelles: new construction. Case octroyé, lodged on 28 February 2005. The decision was notified on 11 October 2005, 225 days after lodging.
réaménager le terrain + construire un équipement pour les services de la Ville, à savoir : un hall pour stockage du matériel lourd, avec 9 emplacements de parking couverts, et un hall technico-administratif (réfectoires, vestiaires, sanitaires)| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 February 2005 | date the file was received |
| Consultation committee | 5 July 2005 | |
| Decision notified | 11 October 2005 | 225 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)