Granted

Houtweg 99

Bruxelles · 04/PFD/1707755 · Permis d'urbanisme délivré par le FD

Houtweg 99, Bruxelles: heavy renovation. Case octroyé, lodged on 29 March 2019. The decision was notified on 12 December 2019, 258 days after lodging.

Modifier le bâtiment du centre de maintenance des bus et trams de la STIB (permis modificatif: 04/PFD/475217).
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on29 March 2019date the file was received
Decision notified12 December 2019258 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mSigns and advertisingplacer 1 mobilier urbain d’information avec support de publicité (BXL0488)2022
152 mFaçade and windowsmodifier l'aspect de la façade d'un immeuble de logements.2022
156 mExtension or raisingmettre en conformité l'extension du commerce (salle de fêtes)2022
168 mTree fellingHet vellen van 2 hoogstammige bomen2025
176 mSigns and advertisingmaintenir un panneau publicitaire éclairé de 9m²2024

Other nearby cases : 04/PU/1948779, 04/PU/1831586, 04/PU/1831395, 06/PU/1943519, 06/PU/1996121, 06/PU/1904779, 04/PU/1956699, 06/PU/1913848, 06/PU/2014348, 06/PU/1800129, 06/SFD/1821885, 04/PU/1841277, 04/PU/1868808, 04/PU/2026845, 04/PU/1956698, 06/PU/1834675, 06/PU/1931301, 06/PU/1927496, 04/GOU_PU/1928930, 06/PU/1898627, 04/PFD/1905293, 04/PU/1851765, 04/PFD/1848758, 06/PU/2043419, 04/PFD/2002932