Granted
Place Arthur Van Gehuchten 4
Bruxelles · 04/PFD/174203 · Permis d'urbanisme délivré par le FD
Place Arthur Van Gehuchten 4, Bruxelles: heavy renovation. Case octroyé, lodged on 6 April 2006. The decision was notified on 4 January 2007, 273 days after lodging.
Restructuration du CHU Brugmann - Pavillon EN - Cabine Haute Tension et Groupes Electrogènes| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 April 2006 | date the file was received |
| Public inquiry | 22 September 2006 – 7 October 2006 | |
| Consultation committee | 17 October 2006 | |
| Decision notified | 4 January 2007 | 273 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)