Rue du Dobbelenberg 123, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 14 July 2020. The decision was notified on 8 January 2021, 178 days after lodging.
Démolir et reconstruire un hall de tri sélectif| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 July 2020 | date the file was received |
| Public inquiry | 15 October 2020 – 30 October 2020 | |
| Consultation committee | 18 November 2020 | |
| Decision notified | 8 January 2021 | 178 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 61 m | Other | Réaménager un parc de stationnement à l'air libre pour véhicules à moteur en dehors de la voie publique comptant 118 emp | 2023 |
| 242 m | Extension or raising | transformer une maison unifamiliale et construire une annexe en façade arrière (mise en conformité) | 2024 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)