Granted

Avenue du Port 108–110

Bruxelles · 04/PFD/1792448 · Permis d'urbanisme délivré par le FD

Avenue du Port 108–110, Bruxelles: other. Case octroyé, lodged on 5 July 2021. The decision was notified on 15 December 2021, 163 days after lodging.

Plaatsen van een hoogspanningscabine zonder transformatoren maar met hoogspanningscellen.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on5 July 2021date the file was received
Decision notified15 December 2021163 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
27 mNew constructionConstruire une nouvelle salle de concert avec un espace d’accueil du public, un espace dédié aux artistes pouvant les lo2021
51 mSigns and advertisingremplacer 1 mobilier urbain d’information avec support de publicité (BXL0535)2021
119 mFaçade and windowsplacer des grilles en façade avant et façade latérale2025
155 mTree fellingAbattre un arbre malade au-dessus d'une voie très fréquentée.2022
205 mChange of useCréation d'un dépôt de patrimoine pour la Maison du Pain, Musée de la Mode et de la Dentelle avec l'ajout d'ouvertures e2022

Other nearby cases : 04/PFD/2032765

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)