Granted
Rue Bruyn 1
Bruxelles · 04/PFD/187234 · Permis d'urbanisme délivré par le FD
Rue Bruyn 1, Bruxelles: new construction. Case octroyé, lodged on 18 December 2007. The decision was notified on 24 February 2009, 434 days after lodging. The project creates 2 726 m² of housing.
Construire un immeuble à appartements.2 726m²
Housing floor area created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 December 2007 | date the file was received |
| Public inquiry | 10 April 2008 – 10 May 2008 | |
| Consultation committee | 20 May 2008 | |
| Decision notified | 24 February 2009 | 434 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 21 m | Subdivision | division de bien | 2024 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)