Granted
Rue du Heysel 104
Bruxelles · 04/PFD/188894 · Permis d'urbanisme délivré par le FD
Rue du Heysel 104, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 7 March 2008. The decision was notified on 19 January 2009, 318 days after lodging. The project creates 169 m² of housing. It removes 1 043 m² of office space.
Démolir un immeuble de bureaux abandonné et construire une école maternelle pour 280 enfants.169m²
Housing floor area created
1 043m²
Office floor area removed
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 March 2008 | date the file was received |
| Public inquiry | 6 June 2008 – 21 June 2008 | |
| Consultation committee | 1 July 2008 | |
| Decision notified | 19 January 2009 | 318 days |
| Office to housing conversion | yes | |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)