Granted
Rue de Verdun
Bruxelles · 04/PFD/190579 · Permis d'urbanisme délivré par le FD
Rue de Verdun, Bruxelles: public space. Case octroyé, lodged on 20 May 2008. The decision was notified on 23 October 2008, 156 days after lodging.
Désenclavement nord de Bruxelles-National Aéroport, dit projet "Diabolo"| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 May 2008 | date the file was received |
| Consultation committee | 8 July 2008 | |
| Decision notified | 23 October 2008 | 156 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.