Granted
Avenue Franklin Roosevelt 50
Bruxelles · 04/PFD/1905792 · Permis d'urbanisme délivré par le FD
Avenue Franklin Roosevelt 50, Bruxelles: façade and windows. Case octroyé, lodged on 22 June 2023. The decision was notified on 14 July 2023, 22 days after lodging.
Remplacer partiellement les châssis du bâtiment F1 sur le campus du Solbosch et ajouter des garde-corps en verre.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 22 June 2023 | date the file was received |
| Decision notified | 14 July 2023 | 22 days |
| Works started | 15 January 2024 | |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 152 m | Heavy renovation | Rénover et réaménager le bâtiment L pour y intégrer la Faculté d'Architecture. | 2023 |
| 166 m | Public space | Réaménager le paysager des abords de quelques bâtiments du Campus Solbosch en retraçant la voirie de desserte et en déga | 2026 |
| 192 m | Tree felling | Abattre l'arbre/thuya y compris l'enlèvement du système racinaire. La raison principale est la sécurité du périmètre. L' | 2022 |
| 195 m | Extension or raising | isoler et modifier le revêtement de façade pour les façades avant et arrière ainsi que le mur d'héberge et la toiture d' | 2026 |
| 212 m | Tree felling | abattre un arbre à haute tige: bouleau (Betula), dans la zone de recul (jardinet avant) | 2025 |
Other nearby cases : 09/PU/1914433, 09/PU/1800723, 09/SFD/1838643, 09/PU/1860137, 09/PU/1800125, 09/PU/2004559, 04/PFD/1833416, 09/PU/1897337, 09/PU/2037823, 09/PU/1851476, 09/PU/1842162, 09/PFD/2027531
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)