Anna Bochdreef

Bruxelles · 04/PFD/1994253 · Permis d'urbanisme délivré par le FD

Anna Bochdreef, Bruxelles: new construction. Case octroyé, lodged on 10 July 2025. The decision was notified on 23 January 2026, 197 days after lodging.

Voorliggende aanvraag betreft een wijziging op de reeds verkregen vergunning voor het bouwen van het Stadsatelier de Ville, met referentie 04/PFD/1932101.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on10 July 2025date the file was received
Public inquiry25 September 2025 – 10 October 2025
Consultation committee22 October 2025
Decision notified23 January 2026197 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mNew constructionConstruire un nouveau "Stadsatelier de Ville" sur le site de Tour et Taxis à Bruxelles.2024
129 mPublic spaceConstruire une nouvelle voirie de circulation entre le parc Tour & Taxis et la rue Dieudonné Lefèvre. Aménager une voiri2026
138 mNew constructionModifier le permis d'urbanisme délivré le 17/12/2009 (permis modificatif du permis initial : 04/AFD/189309) : - Urbanise2023
203 mChange of useCréation d'un dépôt de patrimoine pour la Maison du Pain, Musée de la Mode et de la Dentelle avec l'ajout d'ouvertures e2022
219 mNew constructionConstruire un ensemble mixte comprenant 89 logements, des commerces, de l'activité productive et un parking souterrain d2025

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)