rue du Marais 49–53, Bruxelles: change of use. Case octroyé, lodged on 18 December 2025. The decision was notified on 20 July 2026, 214 days after lodging. It removes 5 038 m² of office space.
Changer l’affectation d’un l’immeuble de bureau en équipement sans modification de volume.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 December 2025 | date the file was received |
| Decision notified | 20 July 2026 | 214 days |
| Works started | 19 August 2026 | |
| Competent authority | BUP |
Timeline
- Application lodged
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 20 m | Public space | placer une rampe pour personnes à mobilité réduite sur le domaine public | 2022 |
| 35 m | Façade and windows | Installation d’un caisson de volet (gris) au rez-de-chaussée | 2025 |
| 47 m | Façade and windows | Restaurer les vitraux de l'atrium du centre Belge de la Bande Dessinée | 2025 |
| 96 m | Other | Dans le cadre des travaux, le propriétaire souhaite procéder à un habillage esthétique de l’échafaudage pendant la durée | 2026 |
| 96 m | Student housing | Rénovation, extension et transformation d'un immeuble de bureaux en logements pour étudiants. | 2023 |
Other nearby cases : 04/PFD/1903841, 04/PFD/2031436, 04/PU/1821734, 04/PFD/1926089, 04/PFU/1967100, 04/PFU/1912838, 04/PFD/1911379, 04/PU/1993866, 04/PFD/1915265, 04/PFD/1994556, 04/PU/1998771, 04/PU/1968326, 04/PU/1962333, 04/PFD/2016654, 04/PFD/2016510, 04/PFD/1916167, 04/PFD/2013392, 04/PFU/1997922, 04/PFU/1915249, 04/PU/1957309, 04/PU/2007135, 04/PU/1990081, 04/PFD/1900090, 04/PU/1868920, 04/SFD/1842614
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)