Rue Bruyn, Bruxelles: new construction. Case octroyé, lodged on 4 February 2009. The decision was notified on 13 October 2010, 616 days after lodging. The project creates 6 464 m² of housing. It comprises 65 dwellings.

Construire un ensemble de 65 logements et d'une crèche à hautes performances énergétique comprenant 53 emplacements de stationnements en sous-sol et 18 emplacements en surface.
The application's own description, in its source language (FR). Source: Nova.
6 464
Housing floor area created
65
Dwellings created
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on4 February 2009date the file was received
Public inquiry4 September 2009 – 19 September 2009
Consultation committee29 September 2009
Decision notified13 October 2010616 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)