Granted
Rue Evers 5–8
Bruxelles · 04/PFD/235861 · Permis d'urbanisme délivré par le FD
Rue Evers 5–8, Bruxelles: new construction. Case octroyé, lodged on 19 August 2009. The decision was notified on 26 April 2010, 250 days after lodging. The project creates 498 m² of housing. It comprises 5 dwellings.
Construire 5 logements à hautes performances énergétiques.498m²
Housing floor area created
5
Dwellings created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 August 2009 | date the file was received |
| Public inquiry | 28 December 2009 – 12 January 2010 | |
| Consultation committee | 19 January 2010 | |
| Decision notified | 26 April 2010 | 250 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)