Boulevard de Nieuport, Bruxelles: public space. Case octroyé, lodged on 16 April 2010. The decision was notified on 2 July 2010, 77 days after lodging.
modifier la structure de la nouvelle passerelle pour piétons et cycliste| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 April 2010 | date the file was received |
| Decision notified | 2 July 2010 | 77 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)