Boulevard Lambermont

Bruxelles · 04/PFD/401578 · Permis d'urbanisme délivré par le FD

Boulevard Lambermont, Bruxelles: new construction. Case octroyé, lodged on 2 March 2011. The decision was notified on 25 August 2011, 176 days after lodging.

Construire un poste à haute tension
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on2 March 2011date the file was received
Decision notified25 August 2011176 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.