Granted
Rue de la Plume 5–29
Bruxelles · 04/PFD/476713 · Permis d'urbanisme délivré par le FD
Rue de la Plume 5–29, Bruxelles: split into dwellings. Case octroyé, lodged on 20 July 2012. The decision was notified on 25 January 2013, 189 days after lodging. It comprises 8 dwellings.
COMPLEXE 39 - PLUME: modifier le permis 04/PFD/244800 (8 logements sociaux passifs)8
Dwellings created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 July 2012 | date the file was received |
| Decision notified | 25 January 2013 | 189 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.