Granted
Kruisberg
Bruxelles · 04/PFD/484285 · Permis d'urbanisme délivré par le FD
Kruisberg, Bruxelles: public space. Case octroyé, lodged on 7 March 2013. The decision was notified on 24 March 2017, 1 478 days after lodging.
EP : Aménager l’ICR, transformer le carrefour en rond-point.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 March 2013 | date the file was received |
| Consultation committee | 18 December 2013 | |
| Decision notified | 24 March 2017 | 1 478 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)