Granted
Rue François-Joseph Navez
Bruxelles · 04/PFD/484801 · Permis d'urbanisme délivré par le FD
Rue François-Joseph Navez, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 20 March 2013. The decision was notified on 13 January 2015, 664 days after lodging.
Démolir une sous-station de traction, construire une sous-station de traction 36kV et abattre 87 arbres| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 March 2013 | date the file was received |
| Consultation committee | 28 October 2014 | |
| Decision notified | 13 January 2015 | 664 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)