Granted
Square du Cardinal Cardijn 6
Bruxelles · 04/PFD/487167 · Permis d'urbanisme délivré par le FD
Square du Cardinal Cardijn 6, Bruxelles: other. Case octroyé, lodged on 14 May 2013. The decision was notified on 8 July 2013, 55 days after lodging.
Placer des conteneurs utilitaires de chantier pour une durée de 6 mois à partir du 01 juin 2013| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 May 2013 | date the file was received |
| Decision notified | 8 July 2013 | 55 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)