Skip to content
Altaica Urban
Granted

Chaussée de Vilvorde 216

Bruxelles · 04/PFD/495390 · Permis d'urbanisme délivré par le FD

Chaussée de Vilvorde 216, Bruxelles: new construction. Case octroyé, lodged on 16 December 2013. The decision was notified on 13 May 2015, 513 days after lodging.

Bouwen van een nieuw industrieel mailcentrum “BRUSSEL X” voor BPOST.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on16 December 2013date the file was received
Public inquiry18 December 2014 – 17 January 2015
Consultation committee28 January 2015
Decision notified13 May 2015513 days
Impact studyyes
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
23 mOtherHet bouwen van een in- en uitrit en de aanpassing van een parking.2023
224 mExtension or raisingréunir et étendre 2 bâtiments industriels existants pour agrandir une activité productive industrielle existante (confis2022
225 mChange of useétendre l'Horeca du rez-de-chaussée jusqu'au 1er étage et modifier l'affectation du 1er étage de logement en commerce (r2024
233 mExtension or raisingd’une part, réaménager un centre de données, modifier les façades, rehausser le local technique, agrandir l’abri à vélos2025
233 mTree fellingabattre 30 arbres à haute tige en vue de construire un datacenter (permis A387/2019 et A536/2020)2024

Other nearby cases : 04/PU/1904421, 04/PU/2000197, 04/PU/2025203

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)