Rue Claessens 127–139, Bruxelles: new construction. Case octroyé, lodged on 9 July 2015. The decision was notified on 30 March 2016, 265 days after lodging. The project creates 10 543 m² of housing. It comprises 102 dwellings.

Construire 102 logements répartis dans 3 immeubles (TIVOLI - lot 3)
The application's own description, in its source language (FR). Source: Nova.
10 543
Housing floor area created
102
Dwellings created
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on9 July 2015date the file was received
Public inquiry1 January 2016 – 16 January 2016
Consultation committee2 February 2016
Decision notified30 March 2016265 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.