Skip to content
Altaica Urban
Granted

Allée du Rubis

Bruxelles · 04/PFD/588824 · Permis d'urbanisme délivré par le FD

Allée du Rubis, Bruxelles: change of use. Case octroyé, lodged on 24 December 2015. The decision was notified on 8 February 2018, 777 days after lodging.

Changer l’affectation d’un garage en atelier et salle de spectacle
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on24 December 2015date the file was received
Public inquiry14 April 2017 – 29 April 2017
Consultation committee9 May 2017
Decision notified8 February 2018777 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingÉtendre et aménager l'espace culturel Braem et créer une rampe de livraison2026
31 mPublic spaceRéaliser des travaux de GIEP (Gestion intégrée des eaux pluviales et végétalisation) sur la cité Modèle à 1020 Laeken.2025
65 mOtherenlever et placer un mat pour antennes d'une hauteur de 16 m sur le toit d'un immeuble2024
65 mOtherenlever et placer un mat pour antennes d'une hauteur de 16 m sur le toit d'un immeuble2024
186 mHeavy renovationRénover lourdement le bâtiment CM8 de la Cité Modèle : - modifier le nombre de logements ; - améliorer les performances2022

Other nearby cases : 04/PU/1896674, 04/PU/1897653, 04/PU/1944121, 04/PU/1858074, 10/PFD/1840306, 10/PU/2028078, 04/PU/1830107, 04/PU/1847891

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)