Bruxelles · 04/PFD/668124 · Permis d'urbanisme délivré par le FD
Val Maria, Bruxelles: tree felling. Case octroyé, lodged on 20 February 2018. The decision was notified on 14 March 2018, 22 days after lodging.
Abattre 11 arbres (populus canadensis) et replanter11 quercus robur| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 February 2018 | date the file was received |
| Decision notified | 14 March 2018 | 22 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 43 m | Heavy renovation | créer une deuxième chambre dans un appartement une chambre; transformer la destination du hall en cuisine (mise en confo | 2022 |
| 71 m | Tree felling | abattre 2 arbres à haute tige | 2021 |
| 71 m | Tree felling | abattre 2 arbres à haute tige | 2022 |
| 122 m | Demolition | Démolir 4 bâtiments existants répartis le long de la rue Mariënsteen et réaménager les terrains, tel que suit : - démoli | 2022 |
| 142 m | Façade and windows | d’une part, remplacer 2 châssis pour les fenêtres à gauche aux étages, la porte d’entrée et la porte de garage (mise en | 2024 |
Other nearby cases : 04/ECO/1842050, 04/PFD/2028186, 04/PFD/1956273, 04/PU/1956572, 04/PFD/1969817, 04/PU/1961992, 04/PU/2040184, 04/PU/1895303, 04/PU/1837465, 04/PU/1951698, 04/PU/1863293
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)