Granted
Avenue de Vilvorde 450
Bruxelles · 04/PFD/668371 · Permis d'urbanisme délivré par le FD
Avenue de Vilvorde 450, Bruxelles: new construction. Case octroyé, lodged on 21 February 2018. The decision was notified on 28 September 2018, 219 days after lodging.
Construire un bâtiment pour une chaudière cogénération.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 21 February 2018 | date the file was received |
| Public inquiry | 1 June 2018 – 16 June 2018 | |
| Consultation committee | 26 June 2018 | |
| Decision notified | 28 September 2018 | 219 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 182 m | New construction | Construire de nouveaux bunkers de stockage avec et sans toiture, la construction de pavés, la création d'espaces verts, | 2023 |
| 183 m | New construction | Construire de nouveaux bunkers de stockage avec et sans toiture, la construction de pavés, la création d'espaces verts, | 2023 |
| 236 m | Other | Poser des 18 câbles 36 kV en terrain privé, plus deux fibres optiques et aménager un revêtement perméable à l’eau. | 2023 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)