Granted
Avenue de Vilvorde 126
Bruxelles · 04/PFD/689763 · Permis d'urbanisme délivré par le FD
Avenue de Vilvorde 126, Bruxelles: heavy renovation. Case octroyé, lodged on 3 July 2018. The decision was notified on 17 September 2019, 441 days after lodging.
Transformer le poste 150/36/11kV de Schaerbeek et réaménager le parc à déchets| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 July 2018 | date the file was received |
| Public inquiry | 17 January 2019 – 1 February 2019 | |
| Consultation committee | 12 February 2019 | |
| Decision notified | 17 September 2019 | 441 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Energy works | Remplacer un transformateur de puissance arrivant en fin de vie qui sera placé sur nouvel encuvement aligné avec les 2 a | 2025 |
| 102 m | Demolition and reconstruction | démolir et reconstruire un container servant de bureau | 2023 |
| 102 m | Demolition and reconstruction | démolir et reconstruire un container servant de bureau | 2023 |
| 128 m | New construction | Placer de nouveaux containers de bureaux en remplacement de containers temporaires sur le site d'Electrabel. | 2023 |
| 172 m | Heavy renovation | renoveren van de wachtloge op de site van Elia | 2022 |
Other nearby cases : 04/PFD/1811399, 04/PFU/1860340, 04/PFD/1965654, 04/PU/1828708
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)