Granted
Parc du Cinquantenaire
Bruxelles · 04/PFU/159202 · Permis d'urbanisme unique délivré par le FD
Parc du Cinquantenaire, Bruxelles: energy works. Case octroyé, lodged on 15 October 2004. The decision was notified on 17 August 2007, 1 036 days after lodging.
Bijvoegen van een groep van 2 schouwen in inox voor de vernieuwing van de verwarmingsinstallatie| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 October 2004 | date the file was received |
| Consultation committee | 3 October 2006 | |
| Decision notified | 17 August 2007 | 1 036 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.